Cleveland Ave W Project Area Final Paving

 Cleveland Avenue W. Area Street Improvements Update – 05-28-2026 Final Paving This Friday –Saturday

Ulland plans to have their paving crew in town on Friday, May 29, at 6:00am to start paving the final lift across the entire project area. Please plan to have all vehicles off the project area roadways by 6:00a.m Friday. The roads will be reopened as they are finished and will be fully accessible later in the day. Crew is planning to get the majority of the streets paved Friday, but will work Saturday to finish, if necessary.

With the Holiday week, recycle day is Friday too. Please place your bins out this evening or by 6:00am in your normal location and Ulland and B&B will coordinate to get it picked up early tomorrow.

If you have questions or concerns, please contact Matt Cole at 507-848-5208 or This email address is being protected from spambots. You need JavaScript enabled to view it., or Emma Sullivan (On-Site Inspector) at 507-810-9158.